AI Computing Power Outpaces Grid Capacity: Hundreds of U.S. Data Centers Build Their Own Natural Gas Plants
U.S. grid connection approvals can take up to a decade, leaving time-sensitive data center developers to bypass public grids and build their own behind-the-meter natural gas power plants. Over 100 such projects have now been announced in the U.S., with total planned installed capacity exceeding 115 gigawatts. This costly shortcut not only drives up carbon emissions and locks in long-term fossil fuel dependence, but ultimately shifts the burden of rising gas prices onto ordinary residents.
When demand for AI computing power is surging, the biggest bottleneck for data center deployment is often not server procurement, but grid connection. The U.S. grid connection approval process can take up to a decade, leading many developers who can't wait to bypass the public grid and build their own natural gas power plants to supply their campuses. The first entity to bring this practice to light was xAI's Memphis campus. As early as 2024, the campus put dozens of natural gas turbines into operation; some equipment had not yet obtained permits at that time, so it was investigated by regulators, and the related lawsuit is still ongoing. At that time, building their own power plants was still a niche practice in the industry, but only two years later, this approach has become an option for many projects. According to statistics from market research firm Cleanview, as of October 2026, U.S. data center developers have announced more than 100 behind-the-meter natural gas power plant projects, with a total planned installed capacity of over 115 gigawatts—more than twice the peak electricity demand of the entire state of California. This wave of project announcements basically started in early 2025. Of course, plans do not equal actual implementation. Among these projects, only 4.9 gigawatts of installed capacity are actually operational, and another 15.8 gigawatts are under construction, so the exact number that will be completed remains uncertain. However, the trend of leading players bypassing the public grid has taken hold, and its impact will last for decades.
Building self-built power plants is inherently more expensive than directly connecting to the grid, and developers are willing to pay a premium for one core reason: speed. Musfika Mishi, a researcher at energy consulting firm BloombergNEF, notes that speed is the biggest driver for data centers choosing on-site power supply currently. Under normal procedures, high-energy data centers must first submit an application to the local grid operator for grid connection. Grid planners need to evaluate existing line loads and calculate supporting new transmission lines, transformers, and other facilities, with the entire evaluation and construction cycle often taking five to seven years, and in some regions even approaching a decade. During this period, developers may also need to bear part of the cost of grid upgrades. The so-called behind-the-meter power plant is built on the property side of the user's electricity meter; the electricity generated is directly supplied to the campus without going through the public grid's transmission and distribution process, which exactly saves the long wait for grid connection. Brendan Pierpont, director of power projects at think tank Energy Innovation, mentions that many developers position these gas power plants as temporary transition solutions that will be retained as backup power sources after grid connection is completed. In essence, it is paying a high price to fill the five to seven-year gap of grid connection. But the industry generally worries about the risk of locking in fossil fuels. Mishi states that even if initially positioned as a transition, after investing significant capital in infrastructure, operators rarely shut down the plants directly; they will likely operate them long-term. The short-term bridge solution is very likely to evolve into decades of fossil fuel dependence.
The climate cost of this shortcut has been calculated. Currently, nuclear power and renewable energy together account for about 40% of the U.S. power grid structure. For the same amount of electricity, carbon emissions from drawing power from the public grid are generally lower than those from self-built natural gas power plants. To make matters worse, there is currently tight supply and demand for gas power generation equipment. Most behind-the-meter projects use less expensive simple-cycle turbines, rarely adopting the combined-cycle turbines that are standard on large public grids. The latter can recover waste heat for secondary power generation, significantly improving energy efficiency. The difference in equipment selection will further increase emissions from these off-grid power plants. BloombergNEF tracking data shows that the total planned installed capacity of global data center on-site gas power plants announced so far is 181 gigawatts, of which 90% of capacity is located in the U.S. If all U.S. planned projects are completed, these plants will emit 345 million tons of carbon dioxide equivalent per year by 2035—152 million tons more than connecting the same load to the public grid. This emission increase exceeds the Netherlands' total annual carbon emissions. For detailed calculation results, see the BloombergNEF report.
Many people think that companies generating their own electricity will not affect ordinary users' energy bills, but this is not the case. Matthias Fripp, global policy research director at Energy Innovation, explains that large-scale increased natural gas demand will drive up overall fuel prices. About 60% of U.S. households rely on natural gas for heating and cooking, so rising gas prices will eventually be passed on to ordinary residents' bills and may even push up electricity prices further. Of course, there are better solutions to the current situation. Mishi mentions that self-built gas power plants can be paired with on-site photovoltaic and energy storage facilities to reduce the start-up time of gas turbines and lower emissions, though the cost accounting of multi-energy combinations is more complex. Fripp's team's recent study also shows that directly deploying renewable energy plus energy storage to meet new electricity demand provides sufficient power reliability and long-term costs lower than fossil fuel solutions. "Data centers need massive power urgently, and the existing grid really can't keep up with this pace," Fripp says. "There are good and bad solutions; rushing to bypass the grid to build behind-the-meter gas power plants is probably the worst option—it raises ordinary people's bills and is also bad for the environment."